  • Kamardanga5

    Kolkata Police Training Academy at Kamardanga

    Name of the Project : Construction of Kolkata Police Training Academy near Kamardanga STP Area in District of Howrah.

    Scheme of the Project : 13th Finance Commission.

    Value of the Project : 71.99 Crores.

    Target of Completion : 28.02.2018

    View Details
  • Correctional Home at Baruipur

    New Central Correctional Home at Baruipur

    Name of the Project : Construction of New Central Correctional Home at Baruipur, District-South 24 Parganas.

    Scheme of the Project : State Plan.

    Value of the Project : 129.09 Crores.

    Target of Completion : 28.02.2018(Phase-2).

    View Details
  • Modification renovation and upgradation of Forensic Science Laboratory, West Bengal

    Name of the Project : Modification renovation and upgradation of Forensic Science Laboratory, West Bengal 

    Scheme of the Project : State Plan.

    Value of the Project : 5.39 Crores.

    Target of Completion : 31.03.2018.

    View Details
  • Regional Forensic Science Laboratory at Durgapur

    Name of the Project : Construction of Regional Forensic Science Laboratory at Durgapur, West Bengal.

    Scheme of the Project : State Plan.

    Value of the Project : 1.92 Crores.

    View Details
  • Construction of Bidhannagar Police Line

    Name of the Project : Construction of Bidhannagar Police Line.

    Scheme of the Project : State Plan.

    Value of the Project : 14.56 Crores.

    Target of Completion : 31.03.2018.

    View Details
  • L.S. Qtr. at Alipurduar

    Name of the Project : Construction of 08 units L.S. Qtr. at Alipurduar.

    Scheme of the Project : 13th Finance Commission.

    Value of the Project : 1.15 Crores.

    Target of Completion : 28.02.2018.

    View Details
  • L.S. Qtr. at SAP 13th Bn. Barjora

    Name of the Project : Construction of 32 units L.S. Qtr. at SAP 13th Bn. Barjora.

    Scheme of the Project : 13th Finance Commission.

    Value of the Project : 4.61 Crores.

    Target of Completion : 31.03.2018.

    View Details
  • L.S. Qtr. at SAP 4th Bn. Raigunj

    Name of the Project : Construction of 08 units L.S. Qtr. at SAP 4th Bn. Raigunj,District-Uttar Dinajpur. 

    Scheme of the Project : 13th Finance Commission.

    Value of the Project : 1.15 Crores.

    View Details
  • L.S. Qtr. at EFR 1ST BN., Salua

    Name of the Project : Construction of 16 units L.S. Qtr. at EFR 1ST BN., SALUA, District-Paschim Medinipur.

    Scheme of the Project : 13th Finance Commission.

    Value of the Project : 2.30 Crores.

    Target of Completion : 28.02.2018.

    View Details
  • L.S. Qtr. at EFR 3RD BN., Salua

    Name of the Project : Construction of 16 units L.S. Qtr. at EFR 3RD BN., Salua, District-Paschim Medinipur. 

    Scheme of the Project : 13th Finance Commission.

    Value of the Project : 2.30 Crores.

    Target of Completion : 28.02.2018.

    View Details
  • L.S. Qtr. Balurghat Police Line

    Name of the Project : Construction of 16 units L.S. Qtr. Balurghat Police Line.

    Scheme of the Project : 13th Finance Commission.

    Value of the Project : 2.30 Crores.

    Target of Completion : 07.04.2018.

    View Details
  • L.S. Qtr. at Arms Police Bridge03

    L.S. Qtr. at Arms Police Brigade, Barrackpore

    Name of the Project : Construction of 32 units L.S. Qtr. at Arms Police Brigade, Barrackpore.

    Scheme of the Project : 13th Finance Commission.

    Value of the Project : 4.61 Crores.

    Target of Completion : 31.03.2018.

    View Details
  • Kalna LS Qtrs 02

    L.S. Qtr. at Kalna Old PS

    Name of the Project : Construction of 08 units L.S. Qtr. at Kalna Old PS, Burdwan.

    Scheme of the Project : 13th Finance Commission.

    Value of the Project : 1.15 Crores.

    Target of Completion : 30.04.2018.

    View Details
  • L.S. Qtr. at Karimpur PS

    Name of the Project : Construction of 08 units L.S. Qtr. at Karimpur P.S., District-Nadia. 

    Scheme of the Project : 13th Finance Commission.

    Value of the Project : 1.15 Crores.

    Target of Completion : 15.04.2018.

    View Details
  • L.S. Qtr. Siliguri Metropolitan Police under Siliguri PC.

    Name of the Project : Construction of 16 units L.S. Qtr. Siliguri Metropolitan Police under Siliguri PC. 

    Scheme of the Project : 13th Finance Commission.

    Value of the Project : 2.30 Crores.

    Target of Completion : 31.03.2018.

    View Details
  • 4th Bn KAP

    Construction of Subsidiary Training Centre, 4th Bn KAP Campus, Salt Lake

    Name of the Project : Construction of Subsidiary Training Centre, 4th Bn KAP Campus, Salt Lake

    Scheme of the Project : State Plan

    Value of the Project : 4.07 Crores.

    Target of Completion Date : 31.10.2020.

    View Details
  • Karaya Police Station

    Renovation and upgradation of Karaya Police Station & Quarters of Kolkata Police.

    Name of the Project : Renovation and upgradation of Karaya Police Station & Quarters of Kolkata Police.

    Scheme of the Project : Renovation 18-19

    Value of the Project : 7.11 Crores.

    Target of Completion Date : 31.12.2020.

    View Details
  • Renovation & Upgradation of Shyambazar Traffic Guard at 115 Bidhan Sarani, Kolkata.

    Renovation & Upgradation of Shyambazar Traffic Guard at 115 Bidhan Sarani, Kolkata.

    Name of Project: Renovation & Upgradation of Shyambazar Traffic Guard at 115 Bidhan Sarani, Kolkata.

    Scheme of the project: Renovation 18-19

    Value of the project:  9588130.00 (Tendered amount)

    Target date of Completion: 03.03.2020

    View Details
  • U.S. Qtr. at Alipurduar

    Name of the Project : Construction of 08 units U.S. Qtr. at Alipurduar.

    Scheme of the Project : 13th Finance Commission.

    Value of the Project : 1.46 Crores.

    Target of Completion : 30.06.2018

    View Details
  • Barjora

    U.S. Qtr. at SAP 13TH, BN., Barjora

    Name of the Project : Construction of 08 units U.S. Qtr. at SAP 13TH, BN., Barjora.

    Scheme of the Project : 13th Finance Commission.

    Value of the Project : 1.46 Crores.

    Target of Completion : 28.08.2018

    View Details
  • U.S. Qtr. at Burdwan RP Line

    Name of the Project : Construction of 08 units U.S. Qtr. at Burdwan RP Line.

    Scheme of the Project : 13th Finance Commission.

    Value of the Project : 1.46 Crores.

    Target of Completion : 31.03.2018.

    View Details
  • Barrack4

    Construction of Model Police Station Building at Deganga

    Name of the Project : Construction of Model Police Station Building at Deganga under the district of North 24 Parganas. 

    Scheme of the Project : MPF 2014-2015.

    Value of the Project : 2.60 Crores.

     

    View Details
  • Alipurduar District

    Construction of four storied Superintendent of Police office in Alipurduar district.

     

    1. Name of Project :- Construction of four storied Superintendent of Police office in Alipurduar district.

    2. Scheme of Project :- 
    3. Value of Project :- 5.80 Cr
    4. Status :- Ongoing
    5. Target of Completion :- December, 2019

     

     

    View Details
  • Construction of 16 units U.S. Qtr. at BANKURA POLICE LINE

    Name of the Project : Construction of 08 units L.S. Qtr. at Bankura Police Line. 

    Scheme of the Project : 13th Finance Commission.

    Value of the Project : 2.93 Crores.

    Target of Completion : 31.07.2018.

     

    View Details
  • 16 units U.S. Qtr. at ARMS POLICE BRIGADE

    Construction of 16 units U.S. Qtr. at ARMS POLICE BRIGADE, BARRACKPORE.

    Name of the Project : Construction of 16 units U.S. Qtr. at ARMS POLICE BRIGADE, BARRACKPORE under the district of North 24 Parganas. 

    Scheme of the Project : 13th Finance Commission.

    Value of the Project : 2.93 Crores.

    Target of Completion : 30.04.2018.

     

    View Details
  • Construction of different works at Digha Mohona Coastal PS

    Name of the Project : Construction of different works (barrack, boundary wall, qtr. etc.) at Digha Mohona Coastal PS under the district of Purba Medinipur. 

    Scheme of the Project : Coastal Security Scheme.

    Value of the Project : 2.47 Crores.

     

    View Details
  • Construction of Office-cum-barrack (Home Guard) in the District of Howrah (Rural)

    Name of the Project : Construction of Office-cum-barrack (Home Guard) in the District of Howrah (Rural). 

    Scheme of the Project : MPF Scheme 2011-12.

    Value of the Project : 0.5 Crores.

    View Details
  • Construction of Office-cum-barrack (Home Guard) in the District of Cooch Behar

    Name of the Project : Construction of Office-cum-barrack (Home Guard) in the District of Cooch Behar. 

    Scheme of the Project : MPF Scheme 2011-12.

    Value of the Project : 0.4 Crores.

    Target of Completion : 31.01.2018.

    View Details
  • Construction of Office-cum-barrack (Home Guard) in the District of Hooghly

    Name of the Project : Construction of Office-cum-barrack (Home Guard) in the District of Hooghly.

    Scheme of the Project : MPF Scheme 2011-12.

    Value of the Project : 0.4 Crores.

    View Details
  • Construction of Rural PS at Jibantala

    Name of the Project : Construction of Rural PS at Jibantala.

    Scheme of the Project : MPF 2010-11.

    Value of the Project : 2.60 Crores.

    Target of Completion : 31.03.2018. 

     

    View Details
  • Home Guard Barrack at Halisahar5

    Construction of Home Guard Barrack at Halisahar in the District of North 24Parganas

    Name of the Project : Construction of Home Guard Barrack at Halisahar in the District of North 24Parganas. 

    Scheme of the Project : MPF SAP 2013-14.

    Value of the Project : 0.85 Crores.

    Target of Completion : 28.02.2018.

     

    View Details
  • Construction of Home Guard Barrack at Siliguri PC

    Name of the Project : Construction of Home Guard Barrack at Siliguri PC. 

    Scheme of the Project : MPF SAP 2013-14.

    Value of the Project : 0.8 Crores.

    Target of Completion : 31.01.2018.

    View Details
  • Construction of Home Guard Barrack at Paschim Medinipur District

    Name of the Project : Construction of Home Guard Barrack at Paschim Medinipur District.

    Scheme of the Project : MPF SAP 2014-15.

    Value of the Project : 0.5 Crores.

    Target of Completion : 31.03.2018.

    View Details
  • Construction of Home Guard Barrack at Bankura District

    Name of the Project : Construction of Home Guard Barrack at Bankura District. 

    Scheme of the Project : MPF SAP 2014-15.

    Value of the Project : 0.55 Crores.

    Target of Completion : 31.03.2018.

     

    View Details
  • 4th Battalion Campus

    Renovation and Up-gradation of Police Housing Estate at 4th Battalion Campus, for Kolkata Armed Police

    Name of the Project : Renovation and Up-gradation of Police Housing Estate at 4th Battalion Campus, for Kolkata Armed Police

    Scheme of the Project : Renovation 18-19

    Value of the Project : 27.70 Crores.

    Target of Completion Date : 31.12.2020.

    View Details
  • Belghoria PHE

    Construction of Multi-Storied Building for Residential Accommodation of SI/ Inspector of Kolkata Police at available land at Belghoria PHE

    Name of the Project : Construction of Multi-Storied Building for Residential Accommodation of SI/ Inspector of Kolkata Police at available land at Belghoria PHE. 

    Scheme of the Project : MPF 2011-12.

    Value of the Project : 18.51 Crores.

    Target of Completion : 28.02.2018.

     

    View Details
  • Construction of Type III quarter & Type V quarters at 4B, Prince Dilwarjha Lane, Kolkata-43

    Name of the Project : Construction of Type III quarter & Type V quarters at 4B, Prince Dilwarjha Lane, Kolkata-43. 

    Scheme of the Project : MPF 2013-14. 

    Value of the Project : 5.92 Crores.

     

     

    View Details
  • Construction of Garia Traffic Guard

    Name of the Project : Construction of Garia Traffic Guard. 

    Scheme of the Project : MPF 2013-14.

    Value of the Project : 3.09 Crores.

    Target of Completion : 11.06.2018.

     

    View Details
  • Construction of Survey Park PS and barrack

    Name of the Project : Construction of Survey Park PS & barrack, Purba Jadavpur Traffic Guard & barrack on the departmental land near Hiland Park, EM Bypass. 

    Scheme of the Project : Mpf 2013-14.

     Value of the Project : 5.90 Crores.

     

    Target of Completion : 31.03.2018.

     

    View Details
  • Physical Infrastructure Development of Police Station under Kolkata Police

    Name of the Project : Physical Infrastructure Development of Police Station under Kolkata Police. 

    Scheme of the Project : MPF 2013-14.

    Value of the Project : 3.55 Crores.

    Target of Completion : 28.02.2018.

     

    View Details
  • Construction of G 4 storied Recruit Training cum Barrack building at within B.T. Lines, Cossipore, Kolkata

    Name of the Project : Construction of G 4 storied Recruit Training cum Barrack building at within B.T. Lines, Cossipore, Kolkata 

    Scheme of the Project : State Plan.

    Value of the Project : 5.46 Crores.

    Target of Completion : 16.09.2019.

     

    View Details
  • Construction of G 4 storied Subsidiary Training Centre at 4th Bn., Campus, Salt Lake

    Name of the Project : Construction of G 4 storied Subsidiary Training Centre at 4th Bn., Campus, Salt Lake.  

    Scheme of the Project : State Plan.

    Value of the Project : 7.67 Crores.

    Target of Completion : 16.09.2019.

     

    View Details
  • Construction of Boundary wall at Margram Police Station

    Name of the Project : Construction of Boundary wall at Margram Police Station in the district of Birbhum 

    Scheme of the Project : State Action Plan 2017-2018.

    Value of the Project : 0.28 Crores.

     

    View Details
  • Boundary by Barbed wire for GOPIMOHAN TEA ESTATE

    Name of the Project : Boundary by Barbed wire for GOPIMOHAN TEA ESTATE, Jaigaon, Alipurduar District. 

    Scheme of the Project : State Plan.

    Value of the Project : 1.55 Crores.

    Target of Completion : 30.06.2018.

     

    View Details
  • Three stotied barrack for CIF at Salboni

    Construction of 2 nos. Three stotied barrack for CIF at Salboni

    Name of the Project : Construction of 2 nos. Three stotied barrack for CIF at Salboni in the Paschim Medinipur District. 

    Scheme of the Project : State Plan.

    Value of the Project : 5.60 Crores.

    Target of Completion : 30.06.2018.

     

    View Details
  • Renovation and up-gradation of Qtrs., barrack and office etc. At Asansole-Durgapur Polcie Lines

    Name of the Project : Renovation and up-gradation of Qtrs., barrack and office etc. At Asansole-Durgapur Polcie Lines.  

    Scheme of the Project : State Plan.

    Value of the Project : 6.53 Crores.

    Target of Completion : 31.03.2018.

     

    View Details
  • Land Development of Asansole Police Line

    Name of the Project : Land Development of Asansole Police Line. 

    Scheme of the Project : State Plan. 

    Value of the Project : 0.22 Crores.

     

     

    View Details
  • District Police Administrative building, Police Lines & Residential Accommodation of Police Personnel of different rank of Purba Medinipur District_5

    District Police Administrative building, Police Lines & Residential Accommodation of Police Personnel of different rank of Purba Medinipur District.

    Name of the Project : District Police Administrative building, Police Lines & Residential Accommodation of Police Personnel of different rank of Purba Medinipur District.  

    Scheme of the Project : State Plan.

    Value of the Project : 48.47 Crores.

    Target of Completion : 31.01.2019.

     

    View Details
  • Security Gate at Mangal Pandey Udyan

    Construction of Security Gate at Mangal Pandey Uddyan, Barrackpore

    Name of the Project : Construction of Security Gate at Mangal Pandey Uddyan, Barrackpore in the North 24 Pargans District. 

    Scheme of the Project : State Plan.

    Value of the Project : 0.32 Crores.

    Target of Completion : 28.02.2018.

    View Details
  • PS

    Construction of a Model Semi-Urban Police Station at Jiaganj

    Name of the Project :Construction of a Model Semi-Urban Police Station at Jiaganj in the District of Murshidabad

    Scheme of the Project : State Plan 2014-15.

    Value of the Project : 3.13 Crores.

    Target of Completion : 31.03.2018 (PS Building Hand Over on 12.09.2017).

    View Details
  • District Correctional Home at Nimtouri_2

    District Correctional Home at Nimtouri

    Name of the Project :District Correctional Home at Nimtouri in the Purba Medinipur District. 

    Scheme of the Project : State Plan.

    Value of the Project : 27.98 Crores.

    Target of Completion : 30.06.2018.

     

    View Details
  • Construction of SP Office at Alipurduar

    Name of the Project : Construction of SP Office at Alipurduar 

    Scheme of the Project : State Plan.

    Value of the Project : 7.64 Crores.

    Target of Completion : 31.05.2018.

     

    View Details
  • Intercom connectivity to all floors, LAN connenctivity including fonfiguration system at Araksha Bhawan

    Name of the Project : Intercom connectivity to all floors, LAN connenctivity including fonfiguration system at Araksha Bhawan 

    Scheme of the Project : State Plan. 

    Value of the Project : 0.11 Crores.

     

     

    View Details
  • Alipurduar Police Line

    Construction of District Police Line at Alipurduar

    Name of the Project : Construction of District Police Line at Alipurduar. 

    Scheme of the Project : State Plan.

    Value of the Project : 42.27 Crores.

    Target of Completion : 02.07.2018.

     

    View Details
  • Construction of one storied barrack at Mograhat PS

    Name of the Project : Construction of one storied barrack at Mograhat PS under South 24 Parganas District. 

    Scheme of the Project : State Plan.

    Value of the Project : 0.49 Crores.

    Target of Completion : 15.01.2018.

     

    View Details
  • Jungle Mahal Safe House

    Construction of Jungle Mahal Safe House at Jhargram PD

    Name of the Project : Construction of Jungle Mahal Safe House at Jhargram PD. 

    Scheme of the Project : State Plan.

    Value of the Project : 2.73 Crores.

    Target of Completion : 30.04.2018.

     

    View Details
  • Construction of a new Officers’ Mess in Swami Vivekananda State Police Academy (SVSPA), Barrackpore

    Name of the Project : Construction of a new Officers’ Mess in Swami Vivekananda State Police Academy (SVSPA), Barrackpore in the North 24 Parganas District. 

    Scheme of the Project : State Plan.

    Value of the Project : 4.62 Crores.

    Target of Completion : 30.09.2018.

     

    View Details
  • Construction of Traffic Headquarter, Bidhannagar

    Name of the Project : Construction of Traffic Headquarter, Bidhannagar.  

    Scheme of the Project : State Plan. 

    Value of the Project : 3.98 Crores.

     

     

    View Details
  • Construction of Office-cum-Residence of S.D.P.O., Khatra

    Name of the Project : Construction of Office-cum-Residence of S.D.P.O., Khatra under Bankura District.  

    Scheme of the Project : State Plan. 

    Value of the Project : 1.44 Crores.

     

     

    View Details
  • Construction of Office-cum-Residence of S.D.P.O., Bishnupur

    Name of the Project : Construction of Office-cum-Residence of S.D.P.O., Bishnupur under Bankura District. 

    Scheme of the Project : State Plan.

    Value of the Project : 1.44 Crores.

    View Details
  • Repair and Maintenance of Digha Police Holiday Home

    Name of the Project : Repair and Maintenance of Digha Police Holiday Home in the Purba Medinipur District. 

    Scheme of the Project : State Plan.

    Value of the Project : 2.42 Crores.

    View Details
  • 2 storied building in the Habra Police Station Campus3

    Construction of 2 storied building in the Habra Police Station Campus

    Name of the Project : Construction of 2 storied building in the Habra Police Station Campus. 

    Scheme of the Project : State Plan. 

    Value of the Project : 3.34 Crores.

     

     

    View Details
  • Construction of dining hall, raising of boundary wall and allied works of Araksha Bhawan

    Name of the Project : Construction of dining hall, raising of boundary wall and allied works of Araksha Bhawan. 

    Scheme of the Project : State Plan.

    Value of the Project : 0.83 Crores.

    Target of Completion : 28.02.2018.

    View Details
  • 02

    Construction of Specialized Indian Reserve Battalion in the district of Birbhum (SIRB)

    Name of the Project : Construction of Specialized Indian Reserve Battalion in the district of Birbhum (SIRB). 

    Scheme of the Project : State Plan.

    Value of the Project : 40.06 Crores.

    Target of Completion : 15.05.2019.

    View Details
  • Construction of Four Storied Unit Head Quarter for Barrackpore Police Commissionerate

    Name of the Project : Construction of Four Storied Unit Head Quarter for Barrackpore Police Commissionerate. 

    Scheme of the Project : State Plan. 

    Value of the Project : 14.47 Crores.

     

     

    View Details
  • Renovation of entire first floor of AB for accommodation of both Traffic Office (HQ, WB and Armed Police HQ, WB)

    Name of the Project : Renovation of entire first floor of AB for accommodation of both Traffic Office (HQ, WB and Armed Police HQ, WB).  

    Scheme of the Project : State Plan.

    Value of the Project : 1.09 Crores.

    Target of Completion : 28.02.2018.

     

    View Details
  • Contruction of Head Quarter for Asansol-Durgaur Police Commissionerate

    Name of the Project : Construction of Head Quarter for Asansol-Durgaur Police Commissionerate. 

    Scheme of the Project : State Plan. 

    Value of the Project : 14.50 Crores.

     

     

    View Details
  • Construction of Residence for Addl. SP, Dakshin Dinajpur at Balurghat.

    Name of the Project :Construction of Residence for Addl. SP, Dakshin Dinajpur at Balurghat.  

    Scheme of the Project : State Plan. 

    Value of the Project : 1.45 Crores.

     

     

    View Details
  • Renovation of Quarter for Senior Officer and construction of a new sentry post cum-rest room, Internal Pathway, Gardening & Boundary wall along the quarters including sanitary plumbing and electrical works at Tollygaunge.

    Name of the Project : Renovation of Quarter for Senior Officer and construction of a new sentry post cum-rest room, Internal Pathway, Gardening & Boundary wall along the quarters including sanitary plumbing and electrical works at Tollygaunge. 

    Scheme of the Project : State Plan. 

    Value of the Project : 0.62 Crores.

     

    View Details
  • Boundary wall (175m.) and renovation of existing boundary wall at Ketugram PS

    Name of the Project : Boundary wall (175m.) and renovation of existing boundary wall at Ketugram PS.  

    Scheme of the Project : State Plan. 

    Value of the Project : 0.21 Crores.

     

    View Details
  • 05

    Construction of Rural PS at Chandrapur

    Name of the Project : Construction of Rural PS at Chandrapur in the district of Birbhum  

    Scheme of the Project : State Plan.

    Value of the Project : 2.52 Crores.

    Target of Completion : 31.05.2018.

    View Details
  • Repair and Maintenance of Civil and Electrical works of FSL Lab, Belgachia Road

    Name of the Project : Repair and Maintenance of Civil and Electrical works of FSL Lab, Belgachia Road 

    Scheme of the Project : State Plan. 

    Value of the Project : 0.02 Crores.

     

     

    View Details
  • 02

    Construction of a Model Rural Police Station at Haringhata

    Name of the Project : Construction of a Model Rural Police Station at Haringhata in the District of Nadia. 

    Scheme of the Project : State Plan 2014-15.

    Value of the Project : 2.60 Crores.

    View Details
  • 02

    Construction of a Model Semi-Urban Police Station Building at Nadanghat

    Name of the Project : Construction of a Model Semi-Urban Police Station  Building at Nadanghat in the District of Burdwan.

     Scheme of the Project : State Plan 2014-15.

     

    Value of the Project : 3.030 Crores.

    Target of Completion : 28.02.2018.

     

    View Details
  • Belda PS Barrack

    Construction of Model Police Station Building at Belda

    Name of the Project : Construction of Model Police Station Building at Belda under Paschim Medinipur District 

    Scheme of the Project : MPF 2014-15.

    Value of the Project : 3.13 Crores.

    Target of Completion : 31.03.2018.

     

    View Details
  • Hostel building for Female Trainees at SVSPA

    Construction of 500 capasity Hostel building for Female Trainees at SVSPA, Barrackpore(Phase-I)

    Name of the Project : Construction of 500 capasity Hostel building for Female Trainees at SVSPA, Barrackpore(Phase-I).

    Scheme of the Project : MPF 2014-15.

    Value of the Project : 1.05 Crores.

    Target of Completion : 31.05.2018

    View Details
  • Malda PS

    Construction of Model Urban PS at Malda District

    Name of the Project : Construction of Model Urban Malda Police Station building at Malda. 

    Scheme of the Project : MPF 2013-14

    Value of the Project : 3.13 Crores.

    Completion Date : 24.04.2017(Barrack & Canteen under const).

    View Details
  • Construction of new building for Raghunathganj Police Station under dist. Murshidabad

    Name of the Project : Construction of new building for Raghunathganj Police Station under the district of Murshidabad. 

    Scheme of the Project : MPF 2013-14.

    Value of the Project : 2.60 Crores.

     

    View Details
  • Construction of Renovation and upgradation of the existing Hariharpara PS building, new barrack and canteen

    Name of the Project : Construction of Renovation and upgradation of the existing Hariharpara PS building, new barrack and canteen under Murshidabad District. 

    Scheme of the Project : MPF 2014-15.

    Value of the Project : 2.56 Crores.

     

    View Details
  • Construction of a Rural Police Station at GOALPUKUR in the District of Uttar Dinajpur

    Name of the Project : Construction of a Rural Police Station at GOALPUKUR in the District of Uttar Dinajpur. 

    Scheme of the Project : State Plan 2014-15.

    Value of the Project : 2.60 Crores.

     

    View Details
  • Police Station Building at NADANGHAT

    Construction of a Model Semi-Urban Police Station Building at NADANGHAT

    Name of the Project : Construction of a Model Semi-Urban Police Station  Building at NADANGHAT in the District of Burdwan 

    Scheme of the Project : State Plan 2014-15. 

    Value of the Project : 3.03 Crores.

     

     

    View Details
  • SP Office

    Construction of Administrative Building and Residential Accommodation for Police Personnel for Jhargram Police District

    Name of the Project : Construction of Administrative Building and
    Residential Accommodation for Police Personnel for Jhargram Police
    District.

    Scheme Of the Project : State Plan 2015-16.

    Value of the Project : Rs. 50.28 Crores.

    View Details
  • Patuli PS

    Construction of Patuli P. S. For Kolkata Police

    Name of the Project : Construction of Patuli P. S. For Kolkata Police (Balance Work).

    Scheme of the Project : MPF (2011-12,14-15).

    Value of the Project : 2.35 Crores.

    Target of Completion Date : 31.03.2020.

    View Details
  • Rajdanga PS

    Construction of building for setting up Rajdanga Police Station, barrack and residential quarters of SI/Sgts. on departmental land of 26 cottah at Kasba, opposite to G.D. Purba Abasan

    Name of the Project : Construction of building for setting up Rajdanga Police Station, barrack and residential quarters of SI/Sgts. on departmental land of 26 cottah at Kasba, opposite to G.D. Purba Abasan.

    Scheme of the Project : MPF(2013-14, 14-15)

    Value of the Project : 7.67 Crores.

    Target of Completion Date : 31.12.2020.

    View Details
  • Bansdroni PS

    Construction of Bansdroni P. S. For Kolkata Police

    Name of the Project : Construction of Bansdroni P. S. For Kolkata police (balance work)

    Scheme of the Project : MPF 2011-12

    Value of the Project : 1.92 Crores.

    Target of Completion Date : 31.01.2020.

    View Details
  • Name of Project :- Construction of Model Rural Police Station Building including Force Barrack & Canteen at Rangli Rangliat under Darjeeling District. 2. Scheme of Project :-  3. Value of Project :- 3,53,90,288 /- 4. Status :- Ongoing 5. Target of Complet

    Construction of Model Rural Police Station Building including Force Barrack & Canteen at Rangli Rangliat under Darjeeling District.

    Name of Project :- Construction of Model Rural Police Station Building including Force Barrack & Canteen at Rangli Rangliat under Darjeeling District.

    2. Scheme of Project :- 
    3. Value of Project :- 3,53,90,288 /-
    4. Status :- Ongoing
    5. Target of Completion :- October, 2019

     

     

    View Details
  • Construction of Administrative Block, Academic and Engineering Block, Store(G 1) and 2 Nos of Barrack (Type A), for Infrastructure of Specialized Indian Reserve Battalion at Rajnagar Police Station, Birbhum. (Phase-1, Part-1)

    Name of the Project : Construction of Administrative Block, Academic and Engineering Block, Store(G 1) and 2 Nos of Barrack (Type A), for Infrastructure of Specialized Indian Reserve Battalion at Rajnagar Police Station, Birbhum. (Phase-1, Part-1)


    Scheme of the Project : State Plan

    Value of the Project : 18.55 Crores.

    Target of Completion : 31.12.2019.

     

    View Details
  • Rajnagar Police Station

    Construction of Administrative Block, Academic and Engineering Block, Store(G 1) and 2 Nos of Barrack (Type A), for Infrastructure of Specialized Indian Reserve Battalion at Rajnagar Police Station, Birbhum. (Phase-1, Part-1)

    Name of the Project : Construction of Administrative Block, Academic and Engineering Block, Store(G 1) and 2 Nos of Barrack (Type A), for Infrastructure of Specialized Indian Reserve Battalion at Rajnagar Police Station, Birbhum. (Phase-1, Part-1)
    Scheme of the Project : State Plan
    Value of the Project :18.55 Crores.

    Target of Completion : 31/12/2019

     

     

    View Details
  • Bamungachi TOP Compound Under Howrah Police Commissionerate

    Construction of Traffic Guard Building at Bamungachi TOP Compound Under Howrah Police Commissionerate

    Name of the Project : Construction of Traffic Guard Building at Bamungachi TOP Compound Under Howrah Police Commissionerate.
    Scheme of the Project : 
    Value of the Project : 1.31 Crores.

    Target of Completion : 31.12.2019

    View Details
  • SIRB

    Construction of Specialized Indian Reserve Battalion at Rajnagar Police Staion , Birbhum [ Auditorium, Hospital, Officers Club, Canteen, Armoury, Commandant Bungalow, Deputy Commandant Bungalow, Asst. Commandant Apartment, Sub Inspector Apartment

    Name of the Project : Construction of Specialized Indian Reserve Battalion at Rajnagar Police Staion , Birbhum [ Auditorium, Hospital, Officers Club, Canteen, Armoury, Commandant Bungalow, Deputy Commandant Bungalow, Asst. Commandant Apartment, Sub Inspector Apartment, Barrack and Allied Works under Phase-1, Part-II]
    Scheme of the Project : State Plan
    Value of the Project : 20.67 Crores.

    Target of Completion : 

    View Details
  • homeguard office cum barrack

    Construction of homeguard office cum barracks at Howrah (rural)

    Name of the Project : Construction of Traffic Guard Building at Bamungachi TOP Compound Under Howrah Police Commissionerate.


    Scheme of the Project : MPF scheme

     
    Value of the Project : 0.44 Crores.

    Target of Completion : 31.01.2020

    View Details
  • Construction of Boundary wall for setting up new SDPO, Uluberia office/ Accommodation of officers and force of EF line in Howrah Rural District along with Centry post and Gate.

    Name of the Project : Construction of Boundary wall for setting up new SDPO, Uluberia office/ Accommodation of officers and force of EF line in Howrah Rural District along with Centry post and Gate.

    Scheme of the Project :


    Value of the Project : 0.38 Crores.

    Target of Completion : 03.03.2020

    View Details
  • Jagatballavpur

    Construction of Model Rural PS at Jagatballavpur under State plan

    Name of the Project : Construction of Model Rural PS at Jagatballavpur under State plan

    Scheme of the Project : State Plan


    Value of the Project : 21.71 Crores.

    Target of Completion : 31.12.2019

    View Details
  • Construction of Model Rural Police Station Building at Lokpur in the District of Birbhum

    Construction of Model Rural Police Station Building at Lokpur in the District of Birbhum

    Name of the Project : Construction of Model Rural Police Station Building at Lokpur in the District of Birbhum

    Scheme of the Project : 


    Value of the Project : 2.46 Crores.

    Target of Completion : 07.12.2019

    View Details
  • 1. Name of Project :- Repair, Renovation and Upgradation of 04 Nos. of two storied LS Qtrs at Kalimpong PS in Kalimpong District (3rd Call). 2. Scheme of Project :-  3. Value of Project :- Rs. 82,40,909 /- 4. Status :- Ongoing 5. Target of Completion :- M

    Repair, Renovation and Upgradation of 04 Nos. of two storied LS Qtrs at Kalimpong PS in Kalimpong District (3rd Call).

     

    1. Name of Project :- Repair, Renovation and Upgradation of 04 Nos. of two storied LS Qtrs at Kalimpong PS in Kalimpong District (3rd Call).

    2. Scheme of Project :- 
    3. Value of Project :- Rs. 82,40,909 /-
    4. Status :- Ongoing
    5. Target of Completion :- March, 2020

     

     

    View Details
  • Wireless Building at Sadar Police Station

    Repair, Renovation & Upgradation of two storied (G 2) Wireless Building at Sadar Police Station in Darjeeling (3rd Call).

     

    1. Name of Project :- Repair, Renovation & Upgradation of two storied (G 2) Wireless Building at Sadar Police Station in Darjeeling (3rd Call).

    2. Scheme of Project :- 
    3. Value of Project :- 22,21,953 /-
    4. Status :- Ongoing
    5. Target of Completion :- February, 2020

     

     

    View Details
  • Dabgram under Jalpaiguri District

    Repair, Renovation & Upgradation of residential building - Family Qtrs - A,B,C (G 3) at 10th Bn., Dabgram under Jalpaiguri District (2nd Call).

     

    1. Name of Project :- Repair, Renovation & Upgradation of residential building - Family Qtrs - A,B,C (G 3) at 10th Bn., Dabgram under Jalpaiguri District (2nd Call).

    2. Scheme of Project :- 
    3. Value of Project :- Rs. 1,26,58,569 /-
    4. Status :- Ongoing
    5. Target of Completion :- March, 2020

     

     

    View Details
  • Debgram Barraks

    Construction of 300 Head R.C Barrack (G 4) at SAP 12 Bn., Dabgram under Jalpaiguri District.

     

    1. Name of Project :- Construction of 300 Head R.C Barrack (G 4) at SAP 12 Bn., Dabgram under Jalpaiguri District.

    2. Scheme of Project :- 
    3. Value of Project :- Rs. 5,99,08,589 /-
    4. Status :- Ongoing
    5. Target of Completion :- January, 2021

     

     

    View Details
  • Debgram Academic Block

    Construction of three storied Academic Block (G 2) at SAP 12 Bn., Dabgram under Jalpaiguri District.

     

    1. Name of Project :- Construction of three storied Academic Block (G 2) at SAP 12 Bn., Dabgram under Jalpaiguri District.

    2. Scheme of Project :- 
    3. Value of Project :- Rs. 5,26,77,030 /-
    4. Status :- Ongoing
    5. Target of Completion :- September, 2020

     

     

    View Details
  • Pulbazar PS

    Construction of Rural Police Station Building with Force Barrack and Canteen at Pulbazar PS of hilly areas in the district of Darjeeling.

     

    1. Name of Project :- Construction of Rural Police Station Building with Force Barrack and Canteen at Pulbazar PS of hilly areas in the district of Darjeeling.

    2. Scheme of Project :- 
    3. Value of Project :- 2,52,96,168 /-
    4. Status :- Ongoing
    5. Target of Completion :- October, 2019

     

     

    View Details
  • Construction of building for setting up Rajdanga Police Station, barrack and residential quarters of SI/Sgts. on departmental land of 26 cottah at Kasba, opposite to G.D. Purba Abasan.

     

    Name of Project: Construction of building for setting up Rajdanga Police Station, barrack and residential quarters of SI/Sgts. on departmental land of 26 cottah at Kasba, opposite to G.D. Purba Abasan. 

    Scheme of the project: MPF 2013-'14 MPF 2014-'15

    Value of the project:  76735050 (Tendered amount)

    Status: ongoing

    Target date of Completion: 31.12.2020

    Completion Date:

    View Details
  • Static pileing load test at Rajdanga PS

    Construction of building for setting up Rajdanga Police Station, barrack and residential quarters of SI/Sgts. on departmental land of 26 cottah at Kasba, opposite to G.D. Purba Abasan.

     

    Name of Project: Construction of building for setting up Rajdanga Police Station, barrack and residential quarters of SI/Sgts. on departmental land of 26 cottah at Kasba, opposite to G.D. Purba Abasan. 

    Scheme of the project: MPF 2013-'14 MPF 2014-'15

    Value of the project:  76735050 (Tendered amount)

    Status: ongoing

    Target date of Completion: 31.12.2020

    Completion Date:

    View Details
  • Belghoria PHE

    Construction of Multi-Storied Buildings for Residential Quarters (Block IV,V,VI) for Sub-Inspector on the available vacant land at Belghoria PHE for Kolkata Police.

     

    Name of Project: Construction of Multi-Storied Buildings for Residential Quarters (Block IV,V,VI) for Sub-Inspector on the available vacant land at Belghoria PHE for Kolkata Police.

    Scheme of the project: MPF 2011-'12MPF2013-'14

    Value of the project:  72551100 (Tendered amount)

    Status: ongoing

    Target date of Completion: 31.03.2020

    Completion Date:

    View Details
  • Construction of boundary wall at sdpo tehatta

    Construction of boundary wall at sdpo tehatta

    View Details
  • Construction of CI official cum residence and garrage cum barrack at krishnaganj

    Construction of CI official cum residence and garrage cum barrack at krishnaganj

    Construction of CI official cum residence and garrage cum barrack at krishnaganj

    View Details
  • Construction of CI Office cum residence and garrage cum barrack at karimpur

    Construction of CI Office cum residence and garrage cum barrack at karimpur

    Construction of CI Office cum residence and garrage cum barrack at karimpur

    View Details
  • Construction of Subsidiary Training Centre, 4th Bn KAP Campus, Salt Lake

    Construction of Subsidiary Training Centre, 4th Bn KAP Campus, Salt Lake

     

    Name of Project: Construction of Subsidiary Training Centre, 4th Bn KAP Campus, Salt Lake

    Scheme of the project: State Plan

    Value of the project:  53778067 (Tendered amount)

    Status: ongoing

    Target date of Completion: 31.10.2020

    Completion Date:

    View Details
  • Construction of 8 unit L.S Quarter at Kasba SAP 4 th Battalion, Raiganj

    Construction of 8 unit L.S Quarter at Kasba SAP 4 th Battalion, Raiganj

     

    Name of the Project : Construction of 8 unit L.S Quarter at Kasba SAP 4 th Battalion, Raiganj 

       

    Scheme of the Project : (13 F.C.)


    Project Status : Ongoing


    Value of the Project : ₹ 84,64,835.00

     

    Target date of Completion : 31.03.2020

     

    View Details
  • Construction of 100 Heads Male Barrack at Islampur P.S IN Uttar Dinajpur District

    Construction of 100 Heads Male Barrack at Islampur P.S IN Uttar Dinajpur District

     

    Name of the Project : Construction of 100 Heads Male Barrack at Islampur P.S IN Uttar Dinajpur District.  

     

    Scheme of the Project : 

     

    Project Status : Ongoing

     

    Value of the Project : ₹ 1,82,60,575.00

     

    Target date of Completion :

    View Details
  • Regional /District Office and Accommodation for West Bengal Police Housing & Infrastructure Development Corporation Limited at Malda Police Line in the District of Malda.

    Regional /District Office and Accommodation for West Bengal Police Housing & Infrastructure Development Corporation Limited at Malda Police Line in the District of Malda.

     

    Name of the Project : Regional /District Office and Accommodation for West Bengal Police Housing & Infrastructure Development Corporation Limited at Malda Police Line in the District of Malda.

     

    Scheme of the Project : State Plan.

     

    Project Status : Ongoing

     

    Value of the Project : ₹ 88,77,586.00

     

    Target date of Completion : 05.08.2020

    View Details
  • Construction of Subsidiary Correctional Home at Chanchal (Part-1)- Construction of Jail Perimeter wall

    Construction of Subsidiary Correctional Home at Chanchal (Part-1)- Construction of Jail Perimeter wall

     

    Name of the Project : Construction of Subsidiary Correctional Home at Chachal -(Part-1) Construction of Jail Perimeter Wall

     

    Scheme of the Project : 

     

    Project Status : Ongoing

     

    Value of the Project : ₹ 8,03,46,311.00

     

    Target date of Completion : 30.04.2020

    View Details
  • Construction of Subsidiary Correction home at Chachal-(Part-2)

    Construction of Subsidiary Correction home at Chachal-(Part-2)

     

    Name of the Project : Construction of Subsidiary Correction home at Chachal-(Part-2)

     

    Scheme of the Project : 

     

    Project Status : Ongoing

     

    Value of the Project : ₹ 11,65,97,435.00

     

    Target date of Completion: 25.08.2020

    View Details
  • Construction of Subsidiary Correctional Home at Chachal -(Part-3)-Construction of three storied Male ward ,Male & Female Staff Dormitory,L.S Quarters,Boumdary Wall,Concrete & Bituminous Road,11 KV Sub-Station etc.

    Construction of Subsidiary Correctional Home at Chachal -(Part-3)-Construction of three storied Male ward ,Male & Female Staff Dormitory,L.S Quarters,Boumdary Wall,Concrete & Bituminous Road,11 KV Sub-Station etc.

     

    Name of the Project : Construction of Subsidiary Correctional Home at Chachal -(Part-3)-Construction of three storied Male ward ,Male & Female Staff Dormitory,L.S Quarters,Boumdary Wall,Concrete & Bituminous Road,11 KV Sub-Station etc.

     

    Scheme of the Project :

     

    Project Status : Ongoing

     

    Value of the Project : ₹ 6,62,28,842.00

     

    Target date of Completion : 25.06.2020

    View Details
  • Repair and Renovation of 01 no Single storied Constable Barrack at Karnajhora Police Line

    Repair and Renovation of 01 no Single storied Constable Barrack at Karnajhora Police Line

     

    Name of the Project : Repair and Renovation of 01 no Single storied Constable Barrack at Karnajhora Police Line

     

    Scheme of the Project :

     

    Project Status : Ongoing

     

    Value of the Project : 

     

    Target date of Completion :

    View Details
  • Repair,Renovation and Upgradation of 02 nos. single storied L.S Qtrs. at Malda PL

    Repair,Renovation and Upgradation of 02 nos. single storied L.S Qtrs. at Malda PL

     

    Name of the Project : Renovation of Lower Sub-Ordinate Quarters and falt at Malda Police Line, District Malda(2 nos. Single Storied Building- 8 flats)

     

    Scheme of the Project :

     

    Project Status : Ongoing

     

    Value of the Project : ₹ 21,70,285.00

     

    Target date of Completion : 30.01.2019

    View Details
  • Repair,Renovation and Upgradation of 03 nos. single storied L.S Qtr at Itahar P.S

    Repair,Renovation and Upgradation of 03 nos. single storied L.S Qtr at Itahar P.S

     

    Name of the Project : Repair, Renovation and Upgradation of Three (03) nos. single Lower Subordinate Quarters at Itahar P.S under Uttar Dinajpur District.

     

    Scheme of the Project :

     

    Project Status : Ongoing

     

    Value of the Project : ₹ 6,61,989.00

     

    Target date of Completion : 26.12.2019

    View Details
  • Repairing and renovation of 5 Nos. Three Storied residential buildings (Type –A Barrack) at Kasba SAP 4th Bn. Raiganj, in the district of Uttar Dinajpur.

    Repairing and renovation of 5 Nos. Three Storied residential buildings (Type –A Barrack) at Kasba SAP 4th Bn. Raiganj, in the district of Uttar Dinajpur.

     

    Name of the Project : Repairing and renovation of 5 Nos. Three Storied residential buildings (Type –A Barrack) at Kasba SAP 4th Bn. Raiganj,  in the district of  Uttar Dinajpur.

     

    Scheme of the Project :

     

    Project Status : Ongoing

     

    Value of the Project : ₹ 2,73,17,275.00

     

    Target date of Completion : 30.06.2020

    View Details
  • Islampur PS under Uttar Dinajpur Dist.

    Repair and renovation and upgradation of 24 nos. LS Qtrs. in Islampur PS under Uttar Dinajpur Dist.

     

    Name of the Project : Repair and renovation and upgradation of 24 nos. LS Qtrs. in Islampur PS under Uttar Dinajpur Dist.  

     

    Scheme of the Project :

     

    Project Status : Ongoing

     

    Value of the Project : 58,92,561.00

     

    Target date of Completion : 28.02.2020

    View Details
  • Karnojora Police Line

    Repair,Renovation and Upgradationof 01 no. (G 1) DIB Office Building at Karnojora PL

     

    Name of the Project : Repair, Renovation,Upgradation of 01 (one) no. (G 1) Storied DIB Office Building at Karnojora Police Line under Uttar Dinajpur District.

     

    Scheme of the Project :

     

    Project Status : Ongoing

     

    Value of the Project : ₹ 5,40,109.00

     

    Target date of Completion : 26.12.2019

    View Details
  • DD Building

    Renovation and Upgradition work of DD building ofKolkata Police HQ, Lalbazar.

     

    Name of the Project :

     

    Scheme of the Project :

     

    Project Status : Ongoing

     

    Value of the Project :

     

    Target date of Completion :

    View Details
  • Renovation and Upgradition of Beniapukur PS & Qrs. Of Kolkata Police.

    Renovation and Upgradition of Beniapukur PS & Qrs. Of Kolkata Police.

     

    Name of the Project :

     

    Scheme of the Project :

     

    Project Status : Ongoing

     

    Value of the Project :

     

    Target date of Completion :

    View Details
  • BORJORA BARRACK WORK CHECKING

    BORJORA BARRACK WORK CHECKING

     

    Name of the Project :

     

    Scheme of the Project :

     

    Project Status : Ongoing

     

    Value of the Project :

     

    Target date of Completion :

    View Details
  • Durgapur battalion

    Durgapur battalion repair, renovation work checking.

     

    Name of the Project :

     

    Scheme of the Project :

     

    Project Status : Ongoing

     

    Value of the Project :

     

    Target date of Completion :

    View Details
  • Boundary wall at SDPO Tehatta

    Boundary wall at SDPO Tehatta

     

    Name of the Project :

     

    Scheme of the Project :

     

    Project Status : Ongoing

     

    Value of the Project :

     

    Target date of Completion :

    View Details
  • Model Urban PS at Ranaghat

    Model Urban PS at Ranaghat

     

    Name of the Project :

     

    Scheme of the Project :

     

    Project Status : Ongoing

     

    Value of the Project :

     

    Target date of Completion :

    View Details
  • CI Office Cum Residence And Garrage Cum Bunglow

    CI Office Cum Residence And Garrage Cum Bunglow At

     

    Name of the Project :

     

    Scheme of the Project :

     

    Project Status : Ongoing

     

    Value of the Project :

     

    Target date of Completion :

    View Details
  • Construction of Subsidiary Training Centre, 4th Bn KAP Campus,

    Construction of Subsidiary Training Centre, 4th Bn KAP Campus,

     

    Name of Project: Construction of Subsidiary Training Centre, 4th Bn KAP Campus, Salt Lake

    Scheme of the project: State Plan

    Value of the project:  53778067 (Tendered amount)

    Status: ongoing

    Target date of Completion: 31.10.2020

    Completion Date:

    View Details
  • Model Urban PS At Ranaghat

    Model Urban PS At Ranaghat

     

    Name of the Project :

     

    Scheme of the Project :

     

    Project Status : Ongoing

     

    Value of the Project :

     

    Target date of Completion :

    View Details
  • Boundary Wall At SDPO Tehatta

    Boundary Wall At SDPO Tehatta

     

    Name of the Project :

     

    Scheme of the Project :

     

    Project Status : Ongoing

     

    Value of the Project :

     

    Target date of Completion :

    View Details
  • Karimpur

    CI Office cum Residence And Garrage Cum Bunglow At Karimpur

     

    Name of the Project :

     

    Scheme of the Project :

     

    Project Status : Ongoing

     

    Value of the Project :

     

    Target date of Completion :